Client: Dun Laoghaire Harbour Company
Value: €135,838

Dun Laoghaire Harbour East Pier Repairs

The site is located at Dún Laoghaire Harbour on the inside face of the East Pier.The works were located below, within and immediately adjacent to the inter-tidal zone requiring deposition of rock armour to facilitate the repair works.

  • Masonry repair works to damaged sections of pier wall.
  • Below deck level, to bed level incorporating dive teams, cranage and rescue personal.
  • This included the installation of hessian bags with dry mix 50N concrete which filled the voids and were held in place using re-bar chemically anchored to the pier
  • Masonry repairs works to damaged sections of pier wall above deck level requiring selective demolition and removal of masonry and repair and replace or modify to match the existing.