Client: Galliford Try/Imtech Joint Venture, Anglian Water
Value: £936,000

Lincoln 4    Lincoln 1

Design and construct the pumping station, river intake temporary works and tunnel between the river intake and the pumping station.

To serve the proposed population growth in the greater Lincoln area, Anglian Water required to construct a new Water Treatment Works in Newton on Trent approximately 8 miles west of Lincoln. As part of this scheme, Ward & Burke Construction were contracted to:

  • Design and construct the pumping station.
  • River intake temporary works.
  • 1200mm diameter tunnel between the river intake and the pumping station.